November 17, 2005AMERENENERGY GENERATINGCOMPANY, EDWARDS POWER STATION,Petitioner,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
The
CAAPP permit application concerns Ameren’s coal-fired power plant at 7800 South CILCOLane in Bartonville, Peoria County.
Ameren has the burden of proof.
415 ILCS 5/40.2(a) (2004); see also 35 Ill.
2
Unless the Board or the hearing officer orders otherwise, the Agency must file an answer,including the entire record of its determination within 30 days after it is served with the petition. The first motion asks thatAmeren be allowed to file an original and four copies instead of the nine copies req...
Allowed