PCB 03-234 Order 06/19/03
DYNEGY MIDWEST GENERATION, INC., (BALDWIN POWER STATION) v. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
Upon receipt of an Illinois Environmental Protection Agency recommendation, the Board granted this facility, located in St. Clair and Randolph Counties, a 45-day provisional variance, subject to conditions, from the 35 Ill. Adm. Code 304.141(a) and the effluent limits in National Pollutant Discharge Elimination System Permit No. IL000004 as they apply to total suspended solids for Outfall 001.
Handle: Document-39373
Owner: Brown, Don (User-14, brownd:DocuShare)DS
Tuesday, June 24, 2003 03:58:44 PM CDT
Tuesday, June 24, 2003 05:39:20 PM CDT
Modified By:
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
June 19, 2003DYNEGY MIDWEST GENERATION, INC.,(BALDWIN POWER STATION),Petitioner,v.
  • ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
  • Such provisional variances shall be issued
within two working days of notification from the Agency.
  • IL000004 as they apply to total suspended solids for
Outfall 001, subject to the following conditions:1.
  • This variance will begin on June 16, 2003, and continue for forty-five (45) days
from that date or until completion of the project, whichever occurs earlier.
  • IT IS SO ORDERED.
If Dynegy chooses to accept this provisional variance, it must execute a Certificate ofAcceptance of all terms and conditions ...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
PCB 03-234 Order 061903.pdf
4
13631
No
Appears In: PCB 03-234
Preferred Version: PCB 03-234 Order 06/19/03