View Properties

PCB 72-131 / PCB 72-132 05/17/72 Order
CRANE PACKING COMPANY (MORTON GROVE PLANT) v. ENVIRONMENTAL PROTECTION AGENCY / CRANE PACKING COMPANY ( CRYSTAL LAKE PLANT ) v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-38208
Owner: Site Administrator (User-2, admin:DocuShare)DS
Wednesday, April 2, 2003 11:01:07 AM CST
Tuesday, April 22, 2003 11:40:48 AM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
May 17, 1972CRANE PACKING COMPANY ) (NORTON GROVE PLANT)v.
  • ) PCB 72—131
ENVIRONMENTAL PROTECTION~AGENCY)CRANE PACKING COMPANY(CRYSTAL LAKE PLANT) ) V.
  • ) PCB 72—132
ENVIRONMENTAL PROTECTION AGENCY)ORDER OF THE BOARD (by Mr.
  • 2.
  • Crane shall submit monthly progress reports to the
Agency until the above—described control equipment is installedand operating, at which time Crane shall submit a final report tothe Agency within thirty (30) days after the described controlequipment is operable.
  • 4. Crane shall file with the Agency a ...