PCB 73-217 07/31/73 Opinion and Order
ILLINOIS POWER COMPANY VERMILLION STATION UNIT No. 2 v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-37758
Owner: Site Administrator (User-2, admin:DocuShare)DS
Tuesday, March 25, 2003 02:18:17 PM CST
Tuesday, April 22, 2003 03:26:54 PM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
July 31, 1973ILLINOIS POWER COMPANYVERMILLION STATIONUNIT No.
  • That station consists
of two pulverized coal-fired units and one oil fired fast startunit.
  • Petitioner further alleges that work is continuing on schedule
for the precipitator on Unit 2.
  • Delivery of the precipitator components
has begun, construction of the foundations is complete andthe structural steel work is underway.
  • Structural
steel construction on the electrostatic precipitator of Unit 2began on June 4, 1973 and many of the components have been delivered.
  • 2 within
60 days of its start—up; Petitioner shall notify the Agency five (5)days in advance of said test and shal...