ILLINOIS POLLUTION CONTROL BOARD
July 31, 1973
ILLINOIS POWER COMPANY
VERMILLION STATION
UNIT No.
2,
Petitioner,
v.
)
PCB 73—217
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr. Seaman):
On May 25,
1973, Petitioner, Illinois Power Company, filed
with this Board its Petition to Extend Variance.
Petitioner
operates an electric power generating station known as Vermillion
Station located in Edgar County,
Illinois.
That station consists
of two pulverized coal-fired units and one oil fired fast start
unit.
On September 30,
1971,
after a hearing had been held,
this
Board entered its Order granting variances,
subject to certain
conditions, for Unit 1 until September
30,
1972, subject to extension
until June
30, 1973 and for Unit
2 until September
30,
1973,
subject
to extension until December 31, 1973.
It
is Unit
2 that is the
subject of this variance request.
Petitioner alleges that it has complied with the conditions
of our previous Order and that it is impossible to complete the
installation of the precipitator on Unit
1 prior to June 30, 1973
and to complete the installation of the precipitator on Unit 2
prior to December 31,
1973.
The precipitator
on Unit
1 was completed
and put into operation in June of
1973 as required by the Order.
Petitioner further alleges that work
is continuing on schedule
for the precipitator on Unit 2.
Delivery of the precipitator com-
ponents has begun,
construction of the foundations is complete and
the structural steel work is underway.
Petitioner states that,
barring unforeseen occurrances beyond Petitioner’s control, the
precipitator for Unit
2 can be completed by December 31,
1973.
Petitioner urges that continued operation of Unit
2
is necessary
and essential if Petitioner is
to maintain the reliability of the
supply of electric power to the public and that maintaining
8—
681
—2—
the reliability of the supply of electric power is
in the public
interest and necessary thereto.
On June
5,
1973,
an Agency representative visited Petitioner’s
facility to observe progress made in completing the electrostatic
precipitators.
The Agency is of the opinion that Petitioner has
made good progress in completing the precipitators.
Structural
steel construction on the electrostatic precipitator of Unit 2
began on June 4,
1973 and many of the components have been delivered.
Unit 2 is scheduled to come off line on November
1,
1973 and the
precipitator on this unit should be completed in time to allow the
unit to come back on line by January 13, 1973.
The Agency has
received no comment from the public concerning this variance.
This Opinion constitutes the findings of fact and conclusions
of law of the Board.
IT IS THE ORDER of the Pollution Control Board that variance
be granted for the continued operation of Petitioner~sUnit 2
until December 31,
1973 subject to the following conditions:
1)
All applicable conditions contained in the order of the
Pollution Control Board in PCB71-197 shall remain in full force
and effect;
2)
Petitioner shall perform a stack test on Unit No.
2 within
60 days of its start—up; Petitioner shall notify the Agency five
(5)
days in advance of said test and shall allow the Agency to observe
the test if it desires.
Petitioner shall provide the results of
said test to the Agency as soon
as they are available to Petitioner.
I,
Christan L. Moffett, Clerk of the Illinois Pollution Control Board,
certify that the a
Opinion and Order was adopted by the Board on
the
~I’~
day of
,
1973, by a vote of
‘/
to
0
8
—
682