  • ILLINOIS POLLUTION CONTROL BOARD
June 14, 1973 ) EXCHANGE NATIONAL BANK OF CHICAGO ) as trustee under its Trust No.
  • The current average flow is 1.9 mgd.
  • The plant provides
alum treatment, primary sedimentation and chlorination.
  • Petitioners’ contracted on
July 31, 1969 to purchase the land for over $1,000,000.
  • The petitioner has an investment in facilities intended to be
used by the entire 6-building complex, We are cognizant of thatconstruction and the losses incurred in investment costs lying unutilized.
  • -3-ORDER
1. Variance from the sewer connection ban order entered onM...
Allowed