ILLINOIS POLLUTION CONTROL BOARD
    June 14,
    1973
    )
    EXCHANGE NATIONAL BANK OF CHICAGO
    )
    as trustee under
    its Trust No.
    23787;
    )
    CRYSTAL POINT OF LAKE FOREST,
    a limited
    )
    partnership and beneficiary of said trust,
    )
    and KATZ-WEISS CONSTRUCTION CORPORATION
    )
    )
    )
    v.
    )
    PCB
    73-15
    )
    )
    ENVIRONMENTAL PROTECTION AGENCY
    )
    )
    INTERIM OPINION AND ORDER OF THE BOARD
    (by Mr.
    Dumelle)
    Petitioners
    seek a variance from this Board’s order entered on
    March
    31,
    1971 in League
    of Women Voters
    v. North Shore Sanitary Dis-
    trict, PCB
    70-7,
    70-12,
    70-13,
    and 70-14.
    That order created
    a
    moratorium on construction in Lake County,
    Illinois by precluding
    any
    additional sewer
    connections
    to the North Shore Sanitary District
    (NSSD),
    Some permits were subsequently authorized by later Bo~ard
    orders.
    Hearing was held on April
    5,
    1973.
    The sanitary sewer extension which serves petitioners’ develop-
    ment is tributary to the Lake Forest sewage treatment plant.
    It
    is
    a
    primary plant with a design average flow of 1.2 mgd and a design flow
    of 3.0 mgd.
    The current average flow is 1.9 mgd.
    The plant provides
    alum treatment,
    primary sedimentation and chlorination.
    During peak
    flow periods partially treated sewage
    is bypassed directly to Lake
    Michigan.
    By September,
    1973, dry weather flow from the Lake Forest
    Plant
    is expected to be diverted to the Clavey Road Plant while excess
    wet weather flow will be treated
    at the Lake Forest Plant.
    In addition to being hydraulically overloaded, the plant produces
    an effluent which
    is high in BOW and suspended solids.
    Operational
    reports for October, 1972 thru. January, 1973 show BOD at
    77,
    31,
    49
    and
    32 mg/i and suspended solids at 43,
    26,
    43, and
    44 mg/i.
    Five
    Agency grab samples taken between May, 1972 and January, 1973 show
    BUD at
    75,
    70,
    50,
    75 and 40 mg/l and suspended solids
    at
    36,
    6,
    15,
    35,
    and
    85 mg/i.
    Petitioners’
    propose to build
    three condominium buildings having
    a total of
    102 apartment units and an estimated additional hydraulic
    load of 30,600
    gallons per day with an additional
    52 pounds per day
    of BUD.
    The total project consists of six buildings,
    three of which
    have already been built, and are occupied.
    Petitioners’
    contracted on
    July 31, 1969 to purchase the land for over $1,000,000.
    The proposed
    8
    26~

    -2-
    development was approved by the Lake Forest City Council on February
    2,
    1970.
    On August
    26, 1970 the project received
    a Lake Forest
    sewer
    permit.
    Petitioners, however, have never received
    a permit from the
    Agency.
    Petitioners,
    in oral representations before the Board have
    stated that
    they have put one condominium building under construction
    at their own risk with completion and use scheduled for April
    1,
    1974.
    They would anticipate starting the remaining two buildings
    this year
    with completion dates being respectively July
    1,
    1974
    and September
    1,
    1974.
    The
    petitioner
    has
    an
    investment
    in
    facilities
    intended
    to
    be
    used
    by
    the
    entire
    6-building
    complex,
    We
    are
    cognizant
    of
    that
    construction
    and
    the losses incurred
    in
    investment
    costs
    lying
    unutilized.
    On
    the
    other
    hand,
    the
    Agency
    points
    out
    that
    increased
    flows
    to
    the
    Lake
    Forest
    plant,
    now
    overloaded,
    will
    only
    worsen
    the
    effluent
    and
    thus
    affect
    Lake
    Michigan.
    The solution,
    of course,
    is to divert the Lake Forest plant to an
    enlarged Clavey Road plant.
    But the details
    as
    to that eventuality
    lie
    in another proceeding not yet before us
    and just postponed for
    additional
    hearings
    to
    la e July
    (North Shore Sanitary District v.
    EPA, PCB 73-134).
    The statutory time
    is about
    to run on the instant
    j3~6ceedingand we must decide.
    Since
    use
    of the building now under construction
    is not to be
    before April
    1,
    1974
    we
    grant
    a variance for that connection,
    We defer
    the decision on the remaining two buildings until August
    15,
    1973 and
    keep
    this proceeding
    open pending completion of PCB
    73-134,
    Counsel
    for the petitioner has orally agreed to a waiver until August
    15,
    1973
    from the 90-day statutory decision
    period.
    This opinion constitutes the
    Board’s
    findings
    of
    fact
    and
    con-
    clusions
    of
    law.

    -3-
    ORDER
    1.
    Variance from the sewer connection ban order entered on
    March 31, 1971
    in League
    of Women Voters
    v. North Shore
    Sanitary District, PCB 70-7,
    etc.,
    is granted to petitioner
    in order to enable connection of one of the three buildings
    remaining to be constructed in petitioner’s project
    as
    alleged in the variance petition filed herein.
    Construction
    of the sewer authorized by this Order may be commenced
    immediately, but shall
    not be put into use prior to April
    1,
    1974.
    2.
    The decision of the Board with respect
    to variance of the
    sewer ban as to the remaining
    two buildings
    is deferred for
    further consideration and order of the Board until August 15,
    1973, upon petitioner’s filing
    a waiver of the 90-day variance
    decision rule to August
    15’,
    1973 within five days
    from the
    date hereof.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control
    Board, hereby certify the above
    Interim Opinion and Order
    were adopted on the
    /i/’~\
    day of June,
    1973 by
    a vote of
    3—o
    ~tanJ~Io:f~
    ~
    Illinois Pollution
    C
    rol Board
    8
    27~

    Back to top