  • ILLINOIS POLLUTION CONTROL BOARD
March 28, 1974 ) CITY OF NASHVILLE ))) v.
  • ) PCB 74-114
)) ENVIRONMENTAL PROTECTION AGENCY )) ORDER OF THE BOARD (by Mr.
  • Petitioner is ordered to submit a verified statement from
the engineer detailing the unit costs utilized to arrive at thisestimate.
  • The information listed above shall be submitted within 35
days from the date of this order.
  • The 90-day decision period set by statute shall run from
the date of filing of the additional information requested.