  • IlLINOIS POLLUTION CON~)LBOARD
April 4, 1975IlLINOIS POWER caViPANY,Petitionerv.
  • ) P05 75—110
ENVIROWMENTAL P~1I’ECTIONAGER~YPespondentORDER OF THE BOARD (by Mr.
  • APP, 3rd (First District, 1974,
No.
  • Petitioner estimates that the project can be operational
nine weeks after shipment.
  • Delay in completing its compliance plan is obviously beyond the
control of Petitioner and this variance will be granted.
  • in the previous Opinion of the Board
to guarantee installation of required air pollutioncontrol equipment.
Allowed