1. reports shall detail progress towards completion ofPet±tioner~scompliance plan.
      2. to guarantee installation of required air pollutioncontrol equipment.

IlLINOIS
POLLUTION CON~)LBOARD
April
4,
1975
IlLINOIS
POWER
caViPANY,
Petitioner
v.
)
P05
75—110
ENVIROWMENTAL
P~1I’ECTIONAGER~Y
Pespondent
ORDER
OF
THE
BOARD
(by
Mr.
Zeitlin)
Petitioner
Illinois
Power
Caipany
filed
this
variance
request
for
its
Wood River
Station
Unit
5,
on
Mrch
7,
1975
The petition
seeks
a
variance
fran
Rule
204
of
the
Board
s Air
Pollution
Regulation,
regarding
sulphur
dioxide
Petitioner
states
that
it
~s
currently
involved
in
federal
violation
proceedings
regardirg
Unit
5,
brought
by
the
United
States
Environmental
Protection
Agenqu
(USEPA)
under
the
Clean Air
Act,
Petitioner
states
that
those
proceedings
are
concerned
with
Rule
204 (c)
(I)
(A)
of
this
Board
s
Air
Pollution
Reoulations.
As
a rasult
of
negotiations
held
in
conjunction
with
those
proceedings,
pobitioner
states
that
it
now intends
to
bring
Unit
S
into
coapliance
with
Rule
204
through
the
use
of
low
sulphur
coal
obtained.
fran
th..e
Western
states,
Those
negotiations
are
still
continuing.
The
Petition
in
this
ratter
does
not,
however,
contain
irore
than
that
staple
statement
regardirg
the
proposed
use
of
western
low-sulphur
coal
as
a carpliance
plan,
Petitioner
feels
that
it
meuld
serve
no
purpose
to
capply
with
Board
Procedural
Rule
401 (a)
(viii),
which
requires
a
detailed
description
of
a
program to
achieve
carpliance,
for
several
reasons,
It
is
claimed
that:
1,
There
is
a rossibility
of
differing
and/or
conflicting
caipliance
plans
arising
out
of
proceedings
before
this
Board
and
the
USEPA.
2,
This
Board has
currently
pending
before
it
proposed
changes
to
Rule
204CR
74-2).
Arrong
other
things,
R
74-2
proposes
a
change
in
cciipliance
dates
for
Rule
204.
3,
The
Illinois
Appellate
Court,
in
Cauronwealth
Edison
~
______
Ill.
APP,
3rd
(First
District,
1974,
No.
~87),
recently
held
Rule
204(c)
(1)
(A)
invalid,
16—329

—2—
Corporation in mid-October,
1974.
Amoco selected Vilter as
supplier of the equipment on the basis of earliest delivery.
In September 1974 Vilter informed Amoco that
the unit
could
not be delivered until mid-January 1975 because
of
production
slippage.
Amoco personnel evaluated the effect of
this three
month delay in mid-November and concluded that the project
could still be completed on time.
On November 27,
1974
Vilter informed Amoco
that the re-
frigeration unit could not be delivered earlier than March 24,
1975.
Amoco authorized overtime charges
in an effort to expedite
delivery but was informed by Vilter that their production
facilities were already on an overtime work schedule.
Petitioner estimates that the project can be operational
nine weeks after shipment.
Based on unreliable past estimates
of delivery, Amoco states that it can not accept the March 24,
1975 delivery date with any confidence.
Therefore,
an additional
three weeks
is requested in addition to the nine weeks to allow
for further shipment delays.
The Agency states that delay in delivery of the refrigeration
unit was beyond the control of Petitioner.
The Agency recommends
granting this variance subject to certain conditions.
No ob-
jection to the grant of this variance has been received by the
Agency.
The record shows that Petitioner has made every good faith
effort possible to expedite delivery of the refrigeration unit.
Delay in completing its compliance plan is obviously beyond the
control of Petitioner and this variance will be granted.
ORDER
It
is
the
Order
of the
Pollution
Control
Board
that
Amoco
Chemicals Corporation
be
granted variance from Rule
204(f) of
the Air Pollution Control Regulations for its Wood River multi-
additive manufacturing facility until June 30, 1975 or such
earlier date as the hydrogen sulfide scrubbing unit is installed
and operational.
This variance is subject to the following conditions~
1.
Petitioner shall apply for all required construction
and operating permits from the Agency.
2.
Petitioner shall submit monthly progress reports to
the Environmental Protection Agency.
Such progress
reports shall detail progress towards completion of
Pet±tioner~scompliance plan.
16 —130

—3—
3.
Upon delivery of the refrigeration unit
Petitioner shall advise the Agency of said
delivery date and the expected date of com-
pletion of the hydrogen sulfide scrubber project.
4.
Petitioner shall keep in effect the $50,000
bond ordered. in the previous Opinion of the Board
to guarantee installation of required air pollution
control equipment.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the a ove Opinion and Order was adopted
this
~
day of
________,
1975 by
a vote of
‘I
to ~

Back to top