  • ILLINOIS POLLUTION CONTROL BOARD
May 15, 1975ALLIED CHEMICAL CORPORATION,Petitioner,v.
  • ) PCB 75—ill
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
  • The record sets forth adequate grounds for a hardship
variance as provided in procedural Rule 401.
  • However, Allied’s petition does not contain a compliance
plan although it has retained Procon, Incorporated,to perform an engineering study which will then be reviewedby Allied’s engineers and go before Allied Board of Directors for approval.
  • In addition,
the Board requests that a final corporate approvedcompliance plan be submitted to the Board on or beforeSeptember 1, 1975.
  • IT IS SO ORDERED.
I, Christan L. Moffett, Cl...