January 10, 1980CENTRAL ILLINOIS PUBLIC SERVICE COMRANY,(Grand Tower Power Station) , (Hutsonville Power Station), Petitioner, PCB 79~246V.
PCB 79~247
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
The contested conditions involve pretreatment,
prior to discharge into an ash pond~of boiler chemical cleaningwastes which are generated only when the boilers are cleanedevery two or three years.
Petitioner alleges
that pretreatment plants cannot be built in time to allow clean~ing of these boilers as scheduled and that it is unlikely thehearings will be concluded in time for decision prior to thescheduled cleanings.
Th...
Allowed
scantmp1
Adobe Portable Document Format (.pdf) - application/pdf