ILLINOIS POLLUTION CONTROL BOARD
    January
    10, 1980
    CENTRAL ILLINOIS PUBLIC SERVICE COMRANY,
    (Grand Tower Power Station)
    ,
    (Hutsonville Power Station),
    Petitioner,
    PCB 79~246
    V.
    PCB 79~247
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD
    (by Dr. Satchell):
    On November 26 and December 20, 1979 Central Illinois
    Public Service
    (CIPS)
    filed motions
    to stay NPDES permit condi~
    tions
    for two plants:
    Grand Tower Power Station and Hutsonville
    Power Station.
    The contested conditions involve pretreatment,
    prior to discharge into an ash pond~of boiler chemical cleaning
    wastes which are generated only when the boilers are cleaned
    every two or three years.
    Cleaning is scheduled for Grand Tower
    in May,
    1980 and Hutsonville in March, 1980.
    Petitioner
    alleges
    that pretreatment plants cannot be built in time to allow clean~
    ing of these boilers as scheduled and that
    it is unlikely the
    hearings will be concluded in time for decision prior to the
    scheduled cleanings.
    On December 12 and 24 the Environmental
    Protection Agency
    (Agency)
    filed objections
    to the motions
    to
    stay.
    These are renewed permits and the contested provisions
    are new.
    The Agency has not pointed to regulations which require
    it to include the contested conditions,
    Since they appear to be
    new discretionary conditions the motions to stay will be granted.
    IT IS SO ORDERED,
    I, Christan
    L. Moffett,
    Clerk of the Illinois Pollution
    Control Board, hereby certify the above Order wa