View Properties

PCB 95-039 01/19/95 Order
W. R. GRACE & CO. - CONN., Grace Construction Products v. ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-18125
Owner: Site Administrator (User-2, admin:DocuShare)DS
Friday, April 19, 2002 08:50:45 AM CDT
Wednesday, April 16, 2003 02:49:09 PM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
January 19, 1995W.
  • R.
  • GRACE & CO.
  • This matter is accepted for hearing.
  • The hearing must be scheduled and completed in a timely
manner, consistent with Board practices and the applicablestatutory decision deadline, or the decision deadline as extendedby a waiver (petitioner may file a waiver of the statutorydecision deadline pursuant to 35 Ill.
  • Any briefing schedule shall provide for final filings as
expeditiously as possible and, in time—limited cases, no laterthan 30 days prior to the decision due date, which is the finalregularly scheduled Board meeting date on or before the statutoryor deferred decision deadline. The Board notes t...
Allowed
scantmp1
Adobe Portable Document Format (.pdf) - application/pdf
6.pdf
4
337986
No
Appears In: PCB 95-039
Preferred Version: PCB 95-039 01/19/95 Order