PCB 80-025 04/03/80 Opinion and Order
CENTRAL ILLINOIS PUBLIC SERVICE COMPANY, (Meredosia Power Station) v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-16076
Owner: Site Administrator (User-2, admin:DocuShare)DS
Friday, December 28, 2001 01:10:28 PM CST
Friday, December 28, 2001 02:07:57 PM CST
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
April 3, 1980CENTRAL ILLINOIS PUBLIC SERVICE COMPANY,(Meredosia Power Station) Petitioner,v.
  • ) PCB 80-25
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
  • The Meredosia power station is a 588 megawatt fossil fueled
electric power plant which is situated in Morgan County.
  • The variance will be granted with conditions.
  • CIPS also requests a variance for the 15 mg/i effluent standard
for TSS contained In Rule 408(a) of Chapter 3.
  • The variance
is requested only for cooling water blowdown and emergency overflowdischarges to the Illinois River from Unit No. December 1979 grab samples averaged 65 mg/i,The Agency recommends that the variance b...
Allowed
schroedk
Adobe Portable Document Format (.pdf) - application/pdf
PCB 80-025 040380 Opinion and Order.pdf
4
378976
No
Appears In: PCB 80-025
Preferred Version: PCB 80-025 04/03/80 Opinion and Order