PCB 73-300 10/18/73 Opinion and Order
MT. CARMEL PUBLIC UTILITY COMPANY v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-37082
Owner: Site Administrator (User-2, admin:DocuShare)DS
Thursday, March 13, 2003 03:27:43 PM CST
Thursday, May 15, 2003 11:34:52 AM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION C~N”ROLBOARD
October 18, 1973MT.
  • It is noted that when
this Board granted the first extension of variance toOctober 31, 1973, we anticipated Petitioner’s presentrequest for a further extension.
  • On August 7, 1973, an Agency representative visited
Petitioner’s facility to observe progress made and todiscuss the progress control program.
  • In obtaining easements, the
Agency is of the opinion that Petitioner has shown goodfaith in developing the 138 KV line and problems encounteredin said development are not self—imposed.
  • This Opinion constitutes the findings of fact and
conclusions of law of the Board.