he in compliance with all relevant regulations byJuly 1, 1973 and shall be used prior to said dateonly for emergency operations when its failure tobe in use would curtail electrical services to theCity of Mascoutah.
1 and 2, the subject of this variance are both coal
fired boilers.
12 — 514
—3—As required by Part 2(a) of the Order in PCB 72-219 Mascoutabpurchased the oil burners for Boiler No.
2.
St. Cyn told the Agency investigator
that all work on the oil conversion had been halted, Petitionerhad not informed the Agency in advance of the cessation ofconversion efforts....