until August 15, 1974, permitting it to discharge BOD5 and suspendedsolids in amounts up to 25 mg/i and 37 mg/l, respectively.
In requesting this short further extension, St.
Charles again
states that it has been unable to obtain delivery of certain criticalparts and equipment.
The Agency also states, though, that the problems
which have occurred in meeting the 25 mg/l and 37 mg/1~limitshave beenthe result of operational difficulties and breakdowns incident to theconstruction project and to new equipment shake—down.
2. Construction of the final tanks discussed in the accom...