ILLINOIS POLLUTION CONTROL BOARD
March 13, 1975
THE
CITY
OF ST. CHARLES,
)
)
Petitioner,
)
)
v.
)
PCB 75—21
)
ENVIRONMENTAL PROTECTION AGENCY,
)
)
Respondent.
)
OPINION & ORDER of the Board (by Mr. Zeitlin)
This Variance Petition was filed by the City of St. Charles (St.
Charles) on January 16, 1975. The Petition asks for a second extension
of a variance originally granted by the Pollution Control Board (Board)
on September 26, 1973, and also for an extension of time in which to
complete construction ordered by the Board in conjunction with its
initial variance grant. Both extensions are requested for the period
January 30, 1975 to Maro~15, 1975.
The Board in City of St. Charles and Swift and Company v. EPA, PCB
73—247, 9 PCB 343 (1973), granted St. Charles a variance from Rule 404(b)
until August 15, 1974, permitting it to discharge BOD5 and suspended
solids in amounts up to 25 mg/i and 37 mg/l, respectively. In that
Order the Board also required that St. Charles complete construction of
final tanks for its plant expansion by August 15, 1974. A performance
bond of $5,000 was required to insure the construction of those tanks.
In the subsequent case of City of St. Charles v. EPA, PCB 74—176,
13 PCB 269 (1974), the variance and construction completion requirements
of PCB 73—247 were both extended until January 30, 1975. In the Opinion
accompaning those extensions, the Board stated that it would serve no
valid purpose to deny such an extension. The Board found that Petitioner
had exercised good faith and pursued compliance with “all deliberate
speed.” 13 PCB at 270. The reason given for the extension granted by
the Board in PCB 74—176 was the delayed delivery of the equipment necessary
to complete construction of the final tanks noted above.
In requesting this short further extension, St. Charles again
states that it has been unable to obtain delivery of certain critical
parts and equipment. Such parts and equipment, ordered by St. Charles
in February of 1974, include motor controls on final tank return sludge
pump, meters for discharge of sludge pump, and Walker process cross
collectors. St. Charles now states that delivery for these items should be
complete by February 15, 1975, and that the project should be completed
and operational no later than March 15, 1975. St. Charles again states
that it has made every effort to complete this project on schedule, and
that it has operated in complete good faith.
16
—
155
—2—
In its Recommendation in this matter, the Environmental Protection
Agency (Agency) states a belief that these delivery delays are in fact
beyond the control of Petitioner. The Agency states that current demand
has left many pollution control devices in short supply. Although the
Board is unwilling to accept, in the absence of concrete proof, that
such a general shortage exists, it is nontheless willing to accept such
an unreputed allegation for the purposes of making its determination in
this case.
The Agency Recommendation did note, however, that Petitioner has
had difficulties in meeting the BOD and suspended solid limfts set by
the Board’s Order in
PCB
73—247 and
continued in
effect under the extension
granted in PCB 74—176. The Agency also states, though, that the problems
which have occurred in meeting the 25 mg/l and 37 mg/1~limitshave been
the result of operational difficulties and breakdowns incident to the
construction project and to new equipment shake—down. The Agency feels
however that these difficulties either have been or will be overcome.
The Board agrees with the Agency that once again it would serve no
purpose to deny this extension. It appears that St. Charles has again
acted in complete good faith, and will soon be in compliance with all
applicable Board Regulations. The period covered under this extension
is quite short, and we feel that no unreasonable damage to the environment
will result if the extension
is
granted.
This Opinion constitutes the findings of fact and conclusions of
law of the Board in this matter.
ORDER
IT IS THE ORDER of the Pollution Control Board that Petitioner City
of St. Charles be granted a variance from Rule 404(b) of the Board’s
Water Pollution Regulations from January 30, 1975 until March
15,
1975,
subject to the following conditions:
1. Petitioner
shall not cause or allow concentration of its effluent
greater than 25 mg/i BOD and 37 mg/i suspended solids.
2. Construction of the final tanks discussed in the accompaning
Opinion shall be completed, and those tanks operating, by March 15,
1975.
3. Petitioner shall arrange to have the bond posted in compliance
with the Board’s Order in PCB 73—247, and extended by the Board’s Order
in PCB 74-~l76, extended to cover installation of equipment and construction
as required by this Order, such bond to be posted within 30 days of the
entry of this Order.
16
—
156
—3—
4. Petitioner shall continue compliance with the conditions stated
in paragraphs 3 and 5 of the Board’s Order in PCB 74—176.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify th~above Opinion & Order were adopted on the
~ day of ~
,
1975 by a vote of 1/ to ~
Q_~1
Christan L. Moffett,J
~
1~4rk
Illinois Pollution C&tk~olBoard
16
—
157