February 11, 1976CPC INTERNATIONAL, INC.,Petitioner,v.
) PCB 75—175
ENVIRONMENTAL PROTECTIONAGENCY, Respondent.
Dan Galatzer appeared on~behalf of Intervenor.
OPINION AND ORDER OF THE BOARD (by Mr.
Petitioner’s process steam
and electricity are supplied by five boilers, two of which are225 MMBTU/hr gas-fired and the others being 332.5 MMBTU/hr pulverized, dry bottom, coal-fired boilers.
Emissions were to be controlled by bag-houses. Petitioner was unable
to obtain a steady source of pelletized solid waste fuel to operateon a regular basis. ORDERIt is the Order of the Board that CPC’s petition for variancefrom Rules 203(g)...
Allowed