March 19, 2015ILLINOIS ENVIRONMENTALPROTECTION AGENCY,Complainant,v.
ILLINOIS POWER RESOURCES
GENERATING, LLC.
See 415 ILCS 5/21(o), 21(p),
22.51, 22.51a, 31.1(c), 42(b)(4), 42(b)(4-5), 55(k) (2012); 35 Ill.
Here, any petition for review was due by March 6, 2015 and March 9,
2015.
Respondents must pay the civil penalty by certified check or money order, made
payable to the Illinois Environmental Protection Trust Fund.
172 Ill. 2d R. 335. The
Board’s procedural rules provide that motions for the Board to reconsider or modify its finalorders may be filed with the Board within 35 days after the order is received.
Allowed