November 20, 2014AMEREN MISSOURI and GOOSE CREEKENERGY CENTER,Petitioner,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
Adm.
Code 105.Subpart C.
In this case, the Agency issued the permit subject to
Conditions 3.1, 4.0, and 7.2, for respondents’ Piatt County facility.
Accordingly,
2though the Board hearing affords petitioner the opportunity to challenge the Agency’s reasonsfor its decision, information developed after the Agency’s decision typically is not admitted athearing or considered by the Board. 2002).Hearings will be scheduled and completed in a timely manner, consistent with thedecision deadline (see 415 ILCS 5/40...