November 6, 2014AMEREN MISSOURI and RACCOONCREEK ENERGY CENTER,Petitioner,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
Adm.
Code 105.SubpartC.
In this case, the Agency issued a permit with
conditions for the Flora facility.
Accordingly, though
2the Board hearing affords petitioner the opportunity to challenge the Agency’s reasons for itsdecision, information developed after the Agency’s decision typically is not admitted at hearingor considered by the Board. 2002).Hearings will be scheduled and completed in a timely manner, consistent with thedecision deadline (see 415 ILCS 5/40.2(c) (2012)), which only petitioners may e...