  • BEFORE THE ILLINOIS POLLUTION CONTROL BOARD
MIDWEST GENERATION, LLC,Petitioner,v.
  • ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
  • Adm.
  • Code§
225.295(b)1 and from the requirement to install and have operational flue gas desulfurization("FGD") equipment on Unit 8 at the Waukegan Generating Station ("Waukegan") byDecember 31,2014, as required at Section 225.296(a)(2).
  • In its Petition, Midwest Generation
stated that it would comply with a system-wide S02 emission rate of 0.38 lb/mmBtu in 2015 and2016.
  • See In re Edison Mission Energy, Case No. ~~ 11, 12, 14, and 17. Accordingly, the installation ofthe Trona injection
system and related work on the ESP for Powerton Uni...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
PCB 13-24,011813 MWG's_Responses_to_the_Board's_Questions.pdf
No
1
3043783
No
Appears In: PCB 2013-024
Preferred Version: PCB 13-24,011813 MWG's_Responses_to_the_Board's_Questions