July 23, 2009AMEREN ENERGY GENERATINGCOMPANY and GRAND TOWER POWERPLANT,Petitioners,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
Pet.
at 3-8.
Ameren challenges the inclusion of these conditions and asks the Board to stay their effect until
ultimately ruling on the merits.
at 3, see Exh. 2.
Exhibit 2 to the petition is a “redlined” version of the permit that indicates the conditions or partsof the conditions Ameren seeks to stay. 2In Community Landfill Co. and City of Morris v. IEPA, PCB 01-48, 01-49, slip op. 2.The Board grants the requested partial stay and permit conditions 3.1.3, 4.0, 5.7.2(b),7.1.3(j), 7.1.5(a)(iii)(A...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf