View Properties

PCB 09-097 Order 050709
Handle: Document-65055
Owner: Brown, Don (User-14, brownd:DocuShare)DS
Monday, May 11, 2009 08:54:14 AM CDT
Monday, May 11, 2009 08:54:24 AM CDT
Modified By:
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
May 7, 2009AMEREN ENERGY GENERATINGCOMPANY and ELGIN ENERGY CENTER,Petitioner,v.
  • ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
  • Adm.
  • Code 105.Subpart C.
  • In this case, the Agency granted a CAAPP renewal permit, subject to
conditions, for Ameren’s Elgin Energy Center.
  • 35 Ill. Adm. Code 101.500(d).
2The Board accepts the petition for hearing. 6, 2001), aff’d sub nom. Unless the Board or the hearing officer orders otherwise, the Agency must file an answer,including the entire record of its determination within 30 days after it is served with the petition.
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
PCB 09-097 Order 050709.pdf
No
1
26919
No
Appears In: PCB 09-097
Preferred Version: PCB 09-097 Order 050709.pdf