April 2, 2009PEOPLE OF THE STATE OF ILLINOIS,Complainant,v.
VITHALBHAI PATEL.,
Respondents.
See 35 Ill.
Adm.
Code 103.300(a).
The Board provided notice of the stipulation,
Thecomplaint alleges that respondent violated these provisions by (1) failing to properly inspect thefacility for the presence of asbestos before commencing demolition and renovation; (2) failing toprovide the Illinois Environmental Protection Agency with notice of renovation and demolitionactivities at least 10 working days before commencing those activities; and (3) failing to properlyhandle regulated asbestos-containing material (RACM) and asbestos-containing was...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf