On August 22, 2007, Dynegy timely filed a petition asking the Board to review the
Agency-issued permit.
To date, the Board has received no response from the Agency regarding
Dynegy’s request for a stay.
Adm. Code 105.214(a). Hearings will be scheduled and
completed in a timely manner, consistent with the decision deadline (see 415 ILCS 5/40(a)(2)(2006)), which only Dynegy may extend by waiver (see 35 Ill. 35 Ill. Adm. Code 105.212(a). If the Agency wishes to seek additional time to file therecord, it must file a request for extension before the date on which the record ...