November 17, 2005SOUTHERN ILLINOIS POWER,Petitioner,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
The CAAPP permit application concerns Southern’s electrical power generating
station located in Williamson County.
Southern has the burden of proof.
415 ILCS 5/40.2(a) (2004); see also 35 Ill.
Unless the Board or the hearing officer orders otherwise, the Agency must file an answer,
including the entire record of its determination within 30 days after it is served with the petition. The Board willreserve ruling on that request to allow for a response from the Agency.