The Board grants the petitioner a provisional variance from 35 Ill.
The Board hereby grants the petitioner a provisional variance beginning on a date in
1998, and continuing for 45 days thereafter, subject to the following conditions:1.
The variance shall begin on a date during 1998 when repair work begins on the
packed biological reactor (PBR) and shall continue for 45 days thereafter untilthe repair work on the treatment plant is completed, whichever occurs first.
Written confirmation of each notice shall be sent within five days to th...