AC 03-013 Opinion and Order 07/08/04
ILLINOIS ENVIRONMENTAL PROTECTION AGENCY v. DAN CADWALLADER
The Board entered a final opinion and order requiring respondent to pay the Board hearing costs in the amount of $384.29 and a civil penalty of $1,500. This order follows the Board's interim order of April 1, 2004, which found that this respondent had violated Section 21(p)(1) of the Environmental Protection Act (415 ILCS 5/21(p)(1) (2002)) at his Putnam County facility.
Handle: Document-43422
Owner: Brown, Don (User-14, brownd:DocuShare)DS
Thursday, July 15, 2004 04:04:47 PM CDT
Wednesday, August 18, 2004 03:38:08 PM CDT
Modified By:
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
July 8, 2004ILLINOIS ENVIRONMENTALPROTECTION AGENCY,Complainant,v.
  • DAN CADWALLADER,
Respondent.
  • The hearing in this case was held on October 29,
2003, at the Putnam County Courthouse in Hennepin.
  • Cadwallader to pay those costs under Section 42(b)(4-5) of the Act.
  • Mr.
  • Cadwallader
must pay this amount by certified check or money order, made payable to theIllinois Environmental Protection Trust Fund. 172 Ill. 2d R. 335. TheBoard’s procedural rules provide that motions for the Board to reconsider or modify its finalorders may be filed with the Board within 35 days after the order is received.
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
AC 03-013 Opinion and Order 070804.pdf
4
29435
No
Appears In: AC 03-013
Preferred Version: AC 03-013 Opinion and Order 07/08/04