| - ILLINOIS POLLUTION CONTROL BOARD
October 17, 1972ENVIRONMENTAL PROTECTION AGENCY ) v.SOUTHERN ILLINOIS POWER COOPERATIVE ) SOUTHERN ILLINOIS POWER COOPERATIVE ))) v.)) ENVIRONMENTAL PROTECTION AGENCY )) INTERIM OPINION & ORDER OF THE BOARD (by Mr.- The plant is expected to consume 250, 000 tons of coal and 60, 000 gallons
of oil during 1972.- SIPC has proposed a time schedule as follows:
Start design May, 1972Sta... |