PCB 71-086 12/09/71 Currie Supplemental Order
ENVIRONMENTAL PROTECTION AGENCY v. STATE LINE FOUNDRIES, INC.
Handle: Document-38418
Owner: Site Administrator (User-2, admin:DocuShare)DS
Monday, April 7, 2003 08:35:10 AM CDT
Thursday, April 10, 2003 08:44:00 AM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
December 9, 1971ENVIRONMENTAL PROTECTION AGENCYv.
  • ) #71—86
STATE LINE FOUNDRIES, INC.
  • The company now informs us that because of the dock
strike the furnace is tied up in the port of New York andtherefore asks for an additional 90 days beyond the end of thestrike in which to complete the program.
  • As recommended
by the Agency, we hereby grant the requested extension on thefollowing conditions:I.
  • The ninety days commence to run with the effective
date ending such strike.
  • 3. Respondent shall within 35 days from receipt of this
order post a new bond in the sum of $50,000 reflectingthe amended forfeiture date as describ...
Allowed