  • ILLINOIS POLLUTION CONTROL BOARD
October 17, 1972FREEMAN COAL MINING CORP.
  • As contemplated by that order, Freeman now petitions
for extension, affirming that it has complied with the conditions of the order.
  • Freeman and its contractor
must do all they can to meet the schedule; if they ultimatelycannot, an extension will be in order upon proof of satisfactory efforts.
  • 2.
  • All conditions of the original order remain in effect.
Allowed