View Properties

PCB 73-558 02/28/74 Opinion and Order
IN THE MATTER OF: PETITION OF VARIANCE FOR: A.B. DICK COMPANY
Handle: Document-36491
Owner: Site Administrator (User-2, admin:DocuShare)DS
Friday, February 28, 2003 10:47:02 AM CST
Friday, May 9, 2003 10:20:53 AM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
February 28, 1974IN THE MATTER OF:PETITIONiOF~i7ARIANCEFOR: ) PCB 73-558A.B.
  • DICK COMPANY
OPINION AND ORDER OF THE BOARD (by Dr.
  • However, shipment
of the equipment was rescheduled four times, and it wasfinally expected to arrive at Petitioners plant on December 28,1973, which was too late to have it installed by December 31, 1973.
  • Effluent
from the cyclone vents directly to the atmosphere.
  • Upon installation of the baghouse,
Petitioner proposes to duct the baghouse effluent into anexisting ethyl alcohol adsorption unit in order to reclaim theeffluent, as well as to reduce the emissions of photochemicallyreactive solvents to l...