  • ILLINOIS POLLUTION CONTROL BOARD
May 29, 1974COMMONWEALTH EDISON COMPANY,Petitioner, ) v.
  • ) PCB 74-11
ENVIRONMENTAL PROTECTION AGENCY,Respondent.
  • The Motion is hereby allowed and Edison is granted
an extension of the interim variance until August 4, 1974 forits Waukegan Station and its Sabrooke Units 1, 2 and 3.
  • The
shutdown dates for Sabrooke Units 2 and 3 wjll now be August 4,1974.
  • If Edison
were required to adhere to the previous interim variance, Sabrookecould experience difficulties in meeting that Station’s summerpeak load requirements.
  • IT IS SO ORDERED.
12—431 —2—I, Christan L. Moffett, Clerk of the...
Allowed
Adobe Portable Document Format (.pdf) - application/pdf
OCR0002.pdf
4
231573
No
Appears In: PCB 74-011
Preferred Version: PCB 74-011 05/29/74 Henss Interim Order