PCB 74-060 04/18/74 Opinion and Order
DONALD McELROY, INC. v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-36037
Owner: Site Administrator (User-2, admin:DocuShare)DS
Monday, February 24, 2003 10:36:13 AM CST
Friday, May 9, 2003 01:21:19 PM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
April 18, 1974DONALD McELROY, INC., ) Petitioner,v.
  • ) PCB 74-60
ENVIRONMENTAL PROTECTION AGENCY, ) Respondent.
  • The burning is done in steel drums
with no pollution control equipment.
  • However, construction of the new incinerator
near its North Chicago storage facility has been deferred becauseestimated costs increased from $50,000 to $125,000.
  • 12— 115
—2—A Recommendation was received from the EnvironmentalProtection Agency (hereinafter Agency) on March 7, 1974.
  • Citizens surrounding the plant indicated they were
unhappy to see the burning resume.”The Agency recommended that this varianc...