  • ILLINOIS POLLUTION CONTROL BOAI~D
April 10, 1975DANViI~E SP~NITARY DISTRICT, ) Petitioner,v.
  • ) PCB 75—139
ENVIRONMENTAL PROTECTION AGENCY,)Respondent.
  • Due to the increased delivery dates and the delay, either
anticipated or actual, in approving the plans and specificationsfor the District’s plant, the District now believes that” anextended schedule for completion of construction is more realistic,with construction to be completed in August, 1978.
  • The District is hereby requested to supply additional
information within forty five (45) days of this Order tosupport its Petition For Variance or it will be subject to dismissal for lack of adequat...