discharges into the Big Muddy River which is a tributary ofthe Mississippi River.
Petitioner states that its proposed
treatment plant is tentatively scheduled for completion inJanuary of 1977.
Petitioner alleges that to require compliance with the
three rules would impose an arbitrary and unreasonablehardship during the period it is proceeding to complete its16 — 222 —3—updated sewage treatment plant.
The Agency recommends
that the Board not require such interim treatment facilitiesbecause the time required t...