March 20, 1997SHELL OIL PRODUCTS COMPANY,Petitioner,v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,Respondent.
The Agency requested the extension "to May 6,
1997, or any other date not more than a total of 90 days from the date of the Agency's finaldetermination."P.A.
88-690 (SB1724), effective January 24, 1995, amends Section 40(a) which
governs the permit appeal process to provide:the 35-day period for petitioning for a hearing may be extendedfor a period of time not to exceed 90 days by written noticeprovided to the Board from the applicant and the Agency withinthe initial appeal period.
In the event that petitioner fails to
file an ap...