(petitioner) filed a notice of extension of
the 35-day appeal period pursuant to Section 40 of the Environmental Protection Act, relatingto a January 29, 1997 Illinois Environmental Protection Agency (Agency) determination.
The Agency requested
the extension "to April 29, 1997, or any other date not more than a total of 90 days from thedate of the Agency's final determination."P.A.
88-690 (SB1724), effective January 24, 1995, amends Section 40(a) which
governs the permit appeal process to provide:the 35-day period for petitioning for ...