UNION ELECTRIC COMPANY, (VENICE POWER PLANT) v. ENVIRONMENTAL PROTECTION AGENCY
Handle: Document-33317
Owner: Site Administrator (User-2, admin:DocuShare)DS
Friday, January 17, 2003 03:49:29 PM CST
Friday, May 9, 2003 10:02:36 AM CDT
Modified By: Site Administrator (User-2, admin:DocuShare)DS
Locked By:
  • ILLINOIS POLLUTION CONTROL BOARD
April 14, 1977UNION ELECTRIC COMPANY,(VENICE POWER PLANT),Petitioner,v.
  • ) PCB 77—92
ENVIRONMENTAL PROTECTION AGENCYORDER OF THE BOARD (by Mr.
  • In an Order herein dated
July 8, 1976 the Board granted Union Electric Company variancefrom the five-year delay prior to hearing required by Rule203(i) (5) .
  • The Board thus accepted the studies submitted to
the Environmental Protection Agency in January of 1976 asPetitioner’s submission under Rule 203(1) (5).
  • There was at the
time of the variance herein no regulations promulgated for theconduct of the mandatory hearing required under Rule 203(1) (5).
  • Such regulations have now been promu...