March 17, 1977McLEAN COUNTY SERVICE COMPANY, ) Petitioner,v.
) PCB 76—270
ENVIRONMENTAL PROTECTION AGENCY, ) Respondent.
Upon discovery of this information
Petitioner formulated a compliance plan and schedule.
The Agency does question the time schedule.
The Agency feels
that the construction and debugging phases of the schedule canbe shortened considerably.
25 — 114
—3—Without a variance, Petitioner has only until April 30,1977 to come into ôompliance with Rule 203(d) (9) (B) ofChapter 2. It is apparent from the facts presented thatPetitioner cannot~make t~iatdeadline with an assured pollutioncontrol effici...