June 28, 1977ENVIRON~4ENTALPROTECTION AGENCY, ) Complainant,v.
) PCB 76-79
CITY OF CHICAGO, a municipalcorporation, Respondent.
Additional testimony was offered by the City for consideration as
mitigating factors in the Board’s final determination.
The Board
26 — 17 —2—finds the City of Chicago in violation of Rule 103(b) (2) of Chapter2, Part I of the Air Regulations for failing to obtain the requisiteAgency permit.
We recognize the delay in the new
generator’s installation and operation resulted from the City’s contracting restrictions.
3. The City of Chicago shall comply with all the
terms of the agreed upon ...