  • ILLINOIS POLLUTION CONTROL BOARD
March 30, 1978OLIN CORPORATION, Petitioner,v.
  • ) PCB 78-6
ENVIRONMENTAL PROTECTIONAGENCY, Respondent.
  • Briefly, the Petitioner originally discharged into the
Des Plaines River from two sources — the main plant sewer whichcarried process and sanitary wastewater and a gypsum pond whichoccasionally overflowed into the river.
  • All but three are completed and the remainin~three were
scheduled for completion by January 31, 1978.
  • In granting a variance beyond July 1, 1977, the Board questions
compliance with federal effluent limitation deadlines establishedin the Clean Water Act at 33 USC §1311.
  • e, Within 45 days of the date of...