  • ILLINOIS POLLUTION CONTROL BOARD
July 20, 1978COMMONWEALTH EDISON COMPANY, )) Petitioner, )) v.
  • ) PCB 77-316
ENVIRONMENTAL PROTECTION ) AGENCY, ) Respondent.
  • In
March of 1977 a coal washer was completed at Mine 10 and thereafter only washed coal has been supplied to the Kincaid Station.
  • Edison estimates that
there are approximately 400,000 tons of mixed washed and unwashedcoal in storage which they propose to burn on a 50—50 basis withknown washed coal until all of the unwashed coal in storage hasbeen utilized.
  • Consultants retained by Edison to evaluate
the impac...