  • ILLINOIS POLLUTION CONTROL BOARD
January 4, 1979ENVIRONMENTAL PROTECTION AGENCY,Complainant,v.
  • ) PCB 76—248
ASHLAND CHEMICAL COMPANY, ) Respondent.
  • The
Third District Appellate Court on October 20, 1978 issued itsmandate reversing the permit denial and ordering issuance ofthe operating permit for a 120 day period.
  • As
to Counts I and II, which allege operation of boilers withoutthe required permits, Ashland argues that the Appellate Courtdecision renders these counts moot.
  • Such an allegation is a defense to the
Complaint and may be proved at hearing, but it is not groundsfor dismissal of the Complaint.
  • IT IS SO ORDERED.