July 9, 1981IN THE MATTER OF:410(c) PETITION FOR DRESDEN ) PCB 79—134NUCLEAR GENERATING STATIONMS.
No members of the public were
present.
On May 26, 1981 the Agency filed a recommendation that
the proposed alternate thermal standard be allowed for one yearsubject to certain conditions.
Units 2 and 3 each have a net generating
capacity of 794 MWe and began operating on August 11, 1970 andOctober 30, 1971, respectively.
Doc.
pp. 18—19).
After October of 1974, both units were primarily operatedin a closed cycle mode. Ewing and l3rill at p. 1.);2. All of the possible operation modes would have anegligibly small impact on p...