  • ILJI1~OIS POLLUTION CONTROL BOARD
September 8, 1983DEPARTMENT OF THE ARMY,Petitioner,V.
  • ) PCB 83—25
ILLINOIS ENVIRONMENTALPROTECTION AGENCY,Respondent.
  • As reasons for extending the time period the Army Corps
urges that, “,,.there is a high probability that dredging theIllinois River may riot be required during the period of thevariance,” and “only in a dredging year will meaningful, during—dredging data be collected from the proposed sampling andmonitoring program”.
  • Thus, the one—year variance is too short to
allow development of “the information contemplated by the Boardin its order (Mot.
  • The Army Corps and Agency request that the prohibition on
open water ...