April 24, 1986IN THE MATTER OF:APPLICATION FOR LAKE MICHIGAN ) PCB 86—60PERMIT NO.
The City filed
responses in opposition to the objection on April 23 and 24, alsorequesting expedited consideration.
The Board
readopted its Order, all Members voting as they did initially.
The project would include placement of
approximately 80,000 tons of armor stone and 10,000 tons of rockto construct revetments and breakwaters, placement of 150,000cubic yards of sand and 50,000 cubic yards of earth fill forbeach nourishment and other facilities and the dredging of 1500yards of material to allow for installation of boat launchingramps.
69.272
—...
Allowed